Your build, mapped out

What happens.
Week by week.

A standard conversion commonly takes 3–4 weeks. Dormers, ensuites, structural complexity and approvals can add time; your written programme will reflect your project.

AI design concept
PRE-START

Ready before arrival

  • Final scope and programme
  • Engineering and key selections
  • Access, protection and logistics
WEEK 01

Structure & access

  • Protection and strip-out
  • Steel, joists and structural works
  • Stair opening and rooflights
WEEK 02

Shape the space

  • Floor deck and partitions
  • Insulation and first-fix services
  • Dormer or ensuite progress where included
WEEK 03

Close & finish

  • Plasterboard and plastering
  • Second-fix carpentry and electrical
  • Stair finishing
WEEK 04

Complete & hand over

  • Final finishes where scoped
  • Inspection and snag closure
  • Certificates and Project Passport
Communication

You know what is next.

The exact sequence can move with inspections, weather and specialist trades. We confirm the live order rather than promising a rigid generic schedule.

Agreed start window
Stage updates
Snag sign-off
Organised handover
Current programme

Now discussing December starts.

Availability is confirmed only when the survey, written scope, contract and booking payment are complete.

Send your attic details
WhatsApp us